How long does it take to install a drive-on-floor system and can I install it myself?

Answer:

We offer a self-install package, including one-day’s on-site instruction and an installation manual, for both ducts and floors.

  1. Generally, the rate of floor installation is about 20 to 25 square metres per man/day so an 18 m x 18 m floor area should take around 16 man-days.
  2. A 20 m long x 3.0 m high duct will take around 10 man days to erect.